DMRC re-invited tenders for electrification work on Krishna Park Extn. Station on Line-8 Extension

Date:

Share post:

NEW DELHI (Metro Rail News): Delhi Metro Rail Corporation (DMRC) has re-invited tenders to supply and commission 25KV AC Traction, 33KV Auxiliary Sub Stations, Associated Cabling and SCADA Systems for Krishna Park Extension Station of Janakpuri West-R. K Ashram corridor (Extn. of Line-8) under Phase-4 of Delhi Metro.

Name of Work – Design, Detail Engineering, Manufacture, Supply, Installation, Testing and Commissioning of 25KV AC Traction (RIGID OHE), 33KV Auxiliary Sub Stations (ASS), Associated Cabling and SCADA Systems for Krishna Park Ext. Underground Station of Janakpuri west to R. K Ashram corridor (Extn. of Line-8) of Phase-IV Delhi MRTS Project.

Important Details –

Contract Number – DE-05R

Approximate cost of work: INR 22.75 Crore

Completion period of the Work: 20 Months

Document Download / Sale Start Date: 09-Aug-2021

Document Download / Sale End Date: 20-Sep-2021

Pre Bid Meeting Date: 27-Aug-2021

Bid Submission Start Date: 09-Sep-2021

Bid Submission End Date: 20-Sep-2021

Bid Opening Date: 21-Sep-2021

For more details and detailed scope of work, interested applicants can download tender documents from the website – https://eprocure.gov.in/eprocure/app.

This is the second time tenders were invited for this work, as the last tender has been cancelled as the bid value of Alstom Transport India was on the higher side in comparison to DMRC estimated cost.

This time DMRC has increased the approximate cost of the work also  and completion period of work is now 20 months.

As mentioned earlier, this contract will be funded by the JICA ( Japan International Cooperation Agency) as a part of loan sanctioned for Phase-4 of Delhi Metro of amount INR 8,390 Crores.

Narendra Shah
Narendra Shahhttps://www.metrorailnews.in
Founder and Managing Editor at Metro Rail News - A Symbroj Media Pvt Ltd. Playing Key role in editorial activities & operation.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Navi Mumbai Metro: A Look Back at Line 1 and Lessons Learned

Introduction Navi Mumbai, as evident by its name itself, is a newly planned & developed city situated in the...

Transforming Lucknow: The Rise of the Metro

Lucknow, the City of Nawabs, enchants with its rich tapestry of history and contemporary charm. Nestled on the...

Shri Anil Kumar Khandelwal Inspects Ongoing Work at Pamban Bridge 

Ramanathapuram (Metro Rail News): During a two-day visit to Southern Railway, Anil Kumar Khandelwal, Member (Infrastructure) of the...

Kolkata Metro: Construction of 170m Long D-Wall completed at Victoria Metro Station

Kolkata (Metro Rail News): The construction work of Victoria Metro Station is progressing swiftly. Recently, The L&T team...