MUMBAI (Metro Rail News): On Thursday, Mumbai Metro Rail Corporation Limited (MMRC) said that it’s 7th package completed 100% tunneling as the alignment achieved its 24th TBM breakthrough at SEEPZ station. MMRC also said that TBM Wainganga-2 completed the final drive of 1.67 km using 1196 rings.

MMRC tweeted saying, “A double milestone for #Metro3. MMRC’s PKG 7 completes 100% tunneling as the alignment achieves its 24th TBM breakthrough at SEEPZ station. TBM Wainganga-2 completed the final drive of 1.67 Kms using 1196 rings. With this tunneling been #MarolNaka #MIDC & #SEEPZ stands completed.”

Last month, Mumbai Metro Rail Corporation Limited (MMRC) achieved 70 percent of tunneling work for the Mumbai Metro-3 (Colaba-Bandra-SEEPZ) corridor of the Mumbai Metro Rail project.

Frauscher Sensor Technology

This has been completed within 24 months, despite innumerable challenges faced during the construction, according to the Metro Line—III authority. Metro 3 project is a 33.5 KMs long underground corridor running along Colaba-Bandra-SEEPZ. The length of the corridor is marked with 27 key stations out of which 26 will be underground and 1 in grade.