JSPL bags contract to supply head-hardened rails for Indore and Bhopal metro

Date:

Share post:

INDORE (Metro Rail News): Jindal Steel & Power Ltd. (JSPL) won the contract in late October to supply 18-meter-long head-hardened rails for the Phase 1 projects of the Indore and Bhopal metro systems.

The Madhya Pradesh Metro Rail Corporation Ltd. (MPMRCL) issued a tender invitation for this contract (Package BHIN03B) in February with a 1022-day (3-year) timeframe and an undetermined estimate. In July, technical bids were opened, exposing two bidders: JSPL and Mitsui & Co. Ltd. It was discovered during the evaluation, completed on October 15, that Mitsui’s technical bids did not adhere to the requirements of the tender.

JSPL’s Financial Bid: Rs. 138,64,71,000 (138.64 crores)

Brief Scope: Supply of Head Hardened Rails 18 m long UIC 60 60E1 profile IRST 12 2009 1080 Grade HH Class A 8120MT for Bhopal and 8425MT for Indore for Bhopal Metro Rail Project and Indore Metro Rail Project.

MPMRCL’s estimate is still unknown, so an assessment of the chance of an LOA getting issued to JSPL is not provided.

Bhopal Metro

Total Requirement: 8120 MT

Supply of 2000 MT (Lot No.2.1.1): 4-5 months

Supply of 4500 MT (Lot No.2.1.2): 18-20 months

Supply of 1620 MT (Lot No.2.1.3): 30-34 months

Indore Metro

Total Requirement: 8425 MT

Supply of 4500 MT (Lot No.2.2.1): 4-5 months

Supply of 1500 MT (Lot No.2.2.2): 18-19 months

Supply of 2425 MT (Lot No.2.2.3): 30-34 months

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Agra Metro Advances with 2 TBM Breakthroughs on Line 1 

Agra (Metro Rail News): Recently, the Agra Metro Phase 1 project witnessed 2 milestones on Line 1 when ...

Chennai Metro’s TBM S81B Achieves Breakthrough at Otteri Station

Chennai ( Metro Rail News): Another day, another achievement. TBM S81 B with the nickname Kolli, commissioned by...

5 Firms Bid For Thane Metro’s DDC-01 Package 

Thane (Metro Rail News): On 29 August, after the opening of technical bids, MMRCL revealed the names of...

MPMRCL MD Inspects Indore Metro from SC-03 to Gandhi Nagar Depot 

Indore (METRO RAIL NEWS): Shri S. Krishna Chaitanya, IAS, Managing Director of Madhya Pradesh Metro Rail Corporation, conducted...