BHOPAL (Metro Rail News): Madhya Pradesh Metro Rail Corporation Ltd. (MPMRCL) awarded Kalpatru Projects International Limited (KPIL)-Gulermak JV a contract worth Rs. 769 crores on March 14, 2024, for the underground tunnelling and construction of Bhopal Metro’s Orange Line.

The BH-04 package of Bhopal Metro Phase 1 involves twin tunnels spanning 3.39 km. It links Sindhi Colony Station to Aish Bagh Crossing Station via two underground stations, Bhopal Junction Station and Nadra Bus Stand. MPMRCL mandates that KPIL—Gulermak JV use at least two tunnel boring machines for six tunnels.

mpmrcl bh04 page 0001 1

Contract

Tender Notification No: 1065/MPMRCL/2023/Package BH-04.

Date: 17.05.2023

Estimated cost – Rs. 892 crore.

Construction deadline –  3.5 years. 

Assignment

The project entails designing and constructing twin tunnels (Up & Down by Shield TBM), cut & cover, cross passages with or without sumps, ramps, and two underground stations for the Bhopal Metro project, including architectural finishing, water supply, sanitary installation, and drainage works along the underground section from Chainage 28+375 to 31+765 for Bhopal Metro Rail Project.

Bids and Bidders

FirmBid (Rs. in Crore)
KPIL – Gulermak JV768.99
Larsen & Toubro (L&T)823.14
ITD Cementation India835.46
Afcons Infrastructure (AIL)847.26
Tata Projects Ltd. (TPL)869.38
Hindustan Construction Company (HCC)917.54

Construction is supported by financing, secured through a €400 million, i.e. Rs. 3,584 crore (approx.) loan from the European Investment Bank in December 2019.

Package BH-04 marks the final civil package for Bhopal Metro’s Orange Line, following previous awards for BH-01 (AIIMS to Subhash Nagar’s viaduct), BH-02 (AIIMS to Subhash Nagar’s stations), BH-03 (Subhash Nagar to Aish Bagh Ramp and Sindhi Colony Ramp to Karond Circle) and BH-06 (construction of a ramp leading to the Subhash Nagar Depot).

The financial bid opening remains pending for the Blue Line’s Package BH-05, which involves constructing the 12.915 km elevated line between Bhadbhada Chauraha and Ratnagiri Tiraha.


Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.

LEAVE A REPLY

Please enter your comment!
Please enter your name here
Captcha verification failed!
CAPTCHA user score failed. Please contact us!

This site uses Akismet to reduce spam. Learn how your comment data is processed.