NHSRCL Completes 100 Km of Viaduct and 250 Kms of Pier Erection on the Mumbai-Ahmedabad Bullet Train Project

Date:

Share post:

NEW DELHI (Metro Rail News): The NHSRCL on Thursday informed that it has already achieved a cumulative milestone of completing 103.24 Km (s) of elevated viaduct and 251.40  Km(s) of Pier erection work on the prestigious Mumbai -Ahmedabad Bullet Train Project. 

Tweet from Railway Minister 

Railways Minister Sh Ashwini Vaishnav tweeted about it on his official X handle. The tweet informs about the update on the MAHSR project until the 21st of November. 

Viaducts

According to NHSRCL, the 100 km long viaduct comprises a 40 m long full-span box and segment girders. The viaducts are supported on piers measuring 10-20 meters in height with a circular diameter of 4-5 meters. 

NHSRCL Bridges Viaduct 04
default

Piers 

250 Km(s) of pier work has also been completed on the Bullet train project. The project entails the construction of more than 465 km (s) of an elevated viaduct out of a total length of 508 km (s) of the MAHSR project. 

NHSRCL Bridges Viaduct 03

Bridges 

The viaducts include bridges constructed over six rivers of Gujarat: 

  1. Par River (Valsad District)
  2. Purna River (Navsari District) 
  3. Mindhola River (Navsari District) 
  4. Ambika River (Navsari District) 
  5. Auranga River (Valsad District) 
  6. Venganiya River (Navsari District) 

Noise Barriers 

NHSRCL has also begun with the installation of noise barriers along the route of the bullet train to reflect and distribute the sound arising out of the high speed of the bullet train. Based on Shinkansen Technology, the noise barriers would be 2-meter high and 1-meter wide concrete panels. These will be erected on either side of the route. 

Tracks 

As per the NHSRCL, laying the Reinforced Concrete (RC) track bed has also started in Surta. It’s the first time a J-slab ballastless track system has been employed in India. 

NHSRCL Bridges Viaduct 02
default

MAHSR

MAHSR is India’s first high-speed railway corridor built between Mumbai and Ahmedabad at an estimated cost of 1.08 lakh crore.


Intrigued by the future of Metro and its impact on our city? Join us at our upcoming InnoMetro event to delve deeper into this vital issue. Stay informed, get involved, and let’s ride the Metro towards a brighter, more sustainable future together.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Texmaco Completes Acquisition of Jindal Rail Infra at Rs. 615 Crore

Texmaco's Vision Mumbai (Metro Rail News): On 25 July, Texmaco Rail & Engineering announced that it had acquired a...

Indian Railways Intends to Launch 50 Hydrogen Trains by 2047

Indian Railways' Plans for Kavach IVRailways' Share in Freight Transportation Mumbai (Metro Rail News): Mr Anil Kumar Khandelwal, Member...

Wabtec Expands Locomotive Services as Gooty Maintenance Shed Starts Operations

Wabtec's Role  Andhra Pradesh (Metro Rail News): Wabtec Corporation (NYSE: WAB) and Indian Railways celebrated the start of locomotive...

Tricity Metro to Feature New Extensions of 6.15 km

Initial Plan for Tricity Metro: Chandigarh (Metro Rail News): Amidst all the delays, the Tricity Metro Project has progressed...