Patna Metro: TBM Mahavir Achieves First Tunnel Breakthrough in Phase I

Date:

Share post:

PATNA (Metro Rail News): The Patna Metro Phase 1 project has achieved a significant milestone with the first tunnel breakthrough of TBM Mahavir at Patna University Metro Station on the 14.05 km Line 2.

Package

This milestone marked the first tunnel breakthrough for the Patna Metro project within the 8 km underground Package PC-03, which connects Rajendra Nagar and Patna Junction Railway Station.  

TBM

TBM DZ1090, nicknamed Mahavir, is a 6.65m diameter Earth Pressure Balance (EPB) machine built by China Railway Construction Heavy Industry Co. Ltd. (CRCHI). 

TBM Mahavir
Patna Metro: TBM Mahavir Achieves First Tunnel Breakthrough in Phase I 3

Assignment

Following the assembly, TBM Mahavir was lowered into its launching shaft at Moin-ul-Haq Station in March 2023. Subsequently, it was deployed for its first assignment with the aim to construct a 1494m portion of the down-line tunnel towards Patna University in April 2023. 

Mahavir TBM Breakthrough
Patna Metro: TBM Mahavir Achieves First Tunnel Breakthrough in Phase I 4

Contract

The Delhi Metro Rail Corporation (DMRC) awarded this Rs. 1989 crore contract to Larsen & Toubro in December 2021 with a 42-month deadline.

Patna Metro Project

The 39.1 km long Patna Metro Phase 1 project features 2 corridors. Line 1 (East-West corridor) spans 16.86 km connecting with 14 stations, while Line 2 (North-South Corridor) covers 14.05 km linking Patna Junction Railway Station and New ISBT with 12 stations. 

With the current progress, the priority section of the Patna Metro Phase I project is likely to be finalized by August 2024, while the entire Phase 1 is anticipated to be completed in 2027.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Texmaco Completes Acquisition of Jindal Rail Infra at Rs. 615 Crore

Texmaco's Vision Mumbai (Metro Rail News): On 25 July, Texmaco Rail & Engineering announced that it had acquired a...

Indian Railways Intends to Launch 50 Hydrogen Trains by 2047

Indian Railways' Plans for Kavach IVRailways' Share in Freight Transportation Mr. Anil Kumar Khandelwal, Member (Infrastructure) of the Railway...

Wabtec Expands Locomotive Services as Gooty Maintenance Shed Starts Operations

Wabtec's Role  Andhra Pradesh (Metro Rail News): Wabtec Corporation (NYSE: WAB) and Indian Railways celebrated the start of locomotive...

Tricity Metro to Feature New Extensions of 6.15 km

Initial Plan for Tricity Metro: Chandigarh (Metro Rail News): Amidst all the delays, the Tricity Metro Project has progressed...