Only 39% of land acquired for Bullet train project

Till date, we have acquired about 39 percent of the land” said by a senior National High-Speed Rail Corporation Ltd. (NHSRCL) official requesting anonymity said

0
385
Ahmedabad Metro
Phase-1 of Ahmedabad Metro is expected to become fully operational by August 2022 as India celebrates its 75th Independence Day.
Advertisement

NEW DELHI (Metro Rail News): Mumbai-Ahmedabad bullet train project which is Prime Minister Narendra Modi’s ambitious project is missing on its deadline of land acquisition as till date only 39 percent of the 1,380 hectares of land required has been acquired.

“Till date, we have acquired about 39 percent of the land” said by a senior National High-Speed Rail Corporation Ltd. (NHSRCL) official requesting anonymity said. NHSRCL has acquired 537 of the 1,387 hectares land required in Maharashtra and Gujarat he said.

The NHSRCL has acquired 471 of 940 hectares of land, while in Maharashtra, it has acquired 66 of 431 hectares, in Gujarat. He said, “Of the nine hectares land required in Dadra and Nagar Haveli, the agency has been unable to acquire even a single piece of land”.

The government had set a deadline for December 2018 to clear the land acquisition roadblock.
buy viagra oral jelly online no prescription
Modi and his Japanese counterpart Shinzo Abe on September 14, 2017, laid the foundation stone of the ambitious Rs 1.08 lakh crore ($17 billion) 508-km long Ahmedabad-Mumbai high-speed rail project.

Japan International Cooperation Agency (JICA) and the Union Railway Ministry have inked a memorandum of understanding (MoU) for the 508-km corridor, with Japan to partially fund the project.

The railways have floated the tenders for the construction of tunneling works, including testing and commissioning for double line high-speed railway using tunnel boring machine (TBM) and New Austrian Tunnelling Method (NATM) between Mumbai underground station at Bandra-Kurla Complex and Shilphata in Maharashtra, the official said.

According to the official, a 21-km-long tunnel will be dug between Boisar and BKC in Mumbai, 7 km of which will be under the sea.

The NHSRCL official said that the design and construction of civil and building works including testing and commissioning of 237 km length of mainline for Mumbai-Ahmedabad High Speed Rail corridor between Zaroli village at Maharashtra-Gujarat border and Vadodara in Gujarat, which is 47 per cent of total length of the project, elevated except one mountain tunnel of about 280 metre, 24 river crossings and 30 road and canal crossings have been floated.

He said the tenders to construct the stations in Gujarat’s Vapi, Bilimora, Surat, and Bharuch have also been floated.

The official said that the work on utility diversions on various locations is progressing well while the work at Sabarmati hub in Ahmedabad has started.

The bullet trains are expected to run at 350 km per hour covering the 508 km stretch in about two hours.

In comparison, trains currently plying on the route take over seven hours to travel the distance, whereas flights take about an hour.