TBM Tapi of Surat Metro Achieves Breakthrough at India’s 2nd Deepest Metro Station

Date:

Share post:

SURAT (Metro Rail News): TBM S94, or TBM Narmada of the Surat metro, achieved the hidden breakthrough for the Suart Metro Phase 1’s 22.7 Km Line 1. 

Assignment 

The TBM S94 was launched in January 2023 from the western shaft of the Kapodra Station. It was assigned the task of building an up-line tunnel from there. From there, it took roughly a year for the TBM to tunnel a length of about 1.5 kms. 

TBM Tapi 01

Labheshwar Chowk 

The TBM has achieved a hidden breakthrough at the unique Labheshwar Chowk Metro Station, which is 30 meters deep, with two platforms and two concourse levels.  It will be 2nd deepest metro station in India after Howrah Metro station of Kolkata Metro’s East-West Corridor. 

SUrat Metro TBM Tapi
S. No Metro StationDeepest 
01.Howrah Metro Station33 meters (Post Completion) 
02.Labheshwar Chowk Metro Station30 meters (Post Completion) 
03.Hauz Khas metro Station 29 meters 

Further Excavation

S94 & S78 have reached the desired position and will be retrieved from the eastern shaft of Surat Metro Station in due course.

Scope of Work 

The TBM S94 & TBM S78 have been assigned to construct six tunnels for the 3.46 km Package CS2 / UG1, awarded in March 2021 by Gujarat Metro Rail Corporation (GMRC). The scope of work also includes the construction of metro stations at Kapodra, Labheshwar Chowk and Central Warehouse.

TBM Tapi 02

Surat Metro

The 41.93 km-long Surat Metro Rail Project Phase 01 has two lines: Sarthana – Dream City- 22.77 km with a total of 20 stations & Bhesan – Saroli-19.26 km with 18 stations. It is expected to be completed in 2027. 


Intrigued by the future of Metro and its impact on our city? Join us at our upcoming InnoMetro event to delve deeper into this vital issue. Stay informed, get involved, and let’s ride the Metro towards a brighter, more sustainable future together.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Chennai Metro: TBM Bhavani Begins Tunneling on Royapettah – R.K. Salai Section of Line 3

TBM Bhavani’s AssignmentInspection of Phase 2Chennai Metro’s Line 3Royapettah metro station Chennai (Metro Rail News): On 21 July, Mr...

Airtel Payments Bank Launches NCMC-enabled Debit and Prepaid Cards in Partnership with DMRC

New Delhi (Metro Rail News): In continuation of the efforts to introduce more digital ticketing solutions for the...

Chennai Metro: Jakson Ltd. Becomes L1 for E&M Contract of Line 5

Location of workBidding ProcessBidders & Bid PriceScope of workChennai Metro Phase 2 Chennai (Metro Rail News): On 22 July,...

RRTS Corridor: Hon’ble Minister Shri Tokhan Sahu Visits Sahibabad-Duhai Section

Delhi-Meerut RRTS Corridor  India’s first Regional Rapid Transit System (RRTS) project is advancing at a rapid pace. Recently, the...